DATE SENT |
DOCUMENTS SENT |
|
1/31/97 |
Check-off list |
|
9/17/97 |
Pre-cruise letter w/forms |
|
10/14/97 |
Radioisotope form |
|
9/24/97 |
Chief Scientist letter |
|
10/31/97 |
Post-cruise letter w/forms |
|
4/25/97 received/approved 10/10/97 Mexican clearance received/approved |
Foreign clearance package* |
Date: Fri, 12 Sep 1997 08:41:32 -0700
From: kris@odf.UCSD.EDU (Kristin Sanborn)
To: restech@sdsioa.ucsd.edu, john@odf.UCSD.EDU, jas@odf.UCSD.EDU
Subject: Equipment Request - New Horizon Montoya
Cc: kris@odf.UCSD.EDU, woodys@odf.UCSD.EDU, erika@odf.UCSD.EDU,
joanne@odf.UCSD.EDU, bob@odf.UCSD.EDU, ron@odf.UCSD.EDU,
doug@odf.UCSD.EDU, frank@odf.UCSD.EDU, dlong@odf.UCSD.EDU,
carl@odf.UCSD.EDU, jswift@odf.UCSD.EDU, shipsked@ucsd.edu
X-Sun-Charset: US-ASCII
************************** ODF *****************************
************************** EQUIPMENT REQUEST *****************************
--------------
PI/REQUESTOR: Tammy Koonce, ResTech EXPEDITION NAME: 9710NH.montoya
for Dr. Montoya Expedition
PHONE: 4-1632 INDEX: ODF USE STS1165(Restechs/Montoya)
E-MAIL: restechs@sdsioa.ucsd.edu
VESSEL: New Horizon TIC: John Boaz, Jim Schmitt (Staging only)
DATES: 20 Oct 1997 to 20 Nov 1997
PORTS: San Diego to Manazillo
Ship returns to San Diego 26 December 1997
__________________________________________________________________________
ODF PERSONNEL REQUIRED: No: 0 ** MT/SRA: ET: DATA/PROG:
__________________________________________________________________________
Equipment Required:
________________________________________________________________________
24 place Rosette Frame, coated
(Tammy Koonce, ResTech, contacted to verify that painted is acceptable)
24 each Bottles 10-liter
?? each Bottles, spares 10-liter
(CONTACT Tammy Koonce, ResTech to find out how many bottles)
1 each Seabird CTD system #A:
CTD 9+ 91878 6800M
Press Digiquartz 67248
Primary Sensors
Temp SBE 3plus 02359
Cond SBE 4C 01919
O2 SBE 13-02-B 130471
Pump SBE 5T xxx
Secondary Sensors
Temp SBE 3-01/F 867
Cond SBE 4-02/O 509
Pump2 SBE 5T 140
1 each Deck unit 11plus 111878
1 each Pylon
1 each Transmissometer #521
1 each Fluorometer
1 each Altimeter, Simrad
__________________________________________________________________________
Additional Information:
PLEASE HAVE ALL CONTACT WITH PI GO THROUGH TAMMY KOONCE.
Deck Unit has a surface PAR interface.
T. Koonce to inform requestor STS does not have a PAR sensor.
Shipping Details (Approx.Dates,etc.): Equipment needs to be on the MELVILLE
for an expedition 29 December 1997 to 5 January 1998.
The MELVILLE will be in Acapulco on 11 December 1997.
Restechs are making shipping arrangements from New Horizon to Melville.
Restech has requested a "break-down" box for shipping.
All equipment is to be returned clean and assembled.
Overboard equipment must be rinsed with fresh water and dried.
__________________________________________________________________________
Taken by: W. Sutherland Request by: K. Sanborn, 21 August 1997
Copies to: Sutherland/Wilson/Digre(Administration),
RTW/Patrick (Calibrations), Boaz(Marine Tech),
Masten(Chemistry), Delahoyde(Computers), Long(Logistics),
Mattson/Schmitt(Electronics), Swift(Science),
Resident Technicians (restech@sdsioa.ucsd.edu),
Ship Scheduling (shipsked@ucsd.edu)
ODF participants: None
** Notify Kristin Sanborn, John Boaz, Jim Schmitt of additions or changes.
internet: ksanborn@ucsd.edu Telephone: (619) 534-1903
jboaz@ucsd.edu (619) 534-1905
jschmitt@ucsd.edu (619) 534-1907