Cruise Plan
Date: Wed, 28 May 1997 13:07:51 -0700 (PDT)
From: Paul Harvey 
X-Sender: pjh@coast
Reply-To: Paul Harvey 
To: resident technicians 
Cc: Louis Zimm , Marine Facilities Shop ,
        sylvia@sio.ucsd.edu, Clinton Winant ,
        "Myrl C. Hendershott" , jim@complex.ucsd.edu,
        Erika Lawson ,
        Charles Coughran , John Lyons ,
        Grant Mills ,
        Daniel Jackson ,
        "Chris L. Freimuth" ,
        "Douglas J. Alden" ,
        "J. Shannon Scott" ,
        Paul Harvey 
Subject: Sproul cruise 16-21 June 97
Mime-Version: 1.0


Bob,
	We are able to use either .322 or .225 wire for the CTD operations
on the Internal Waves cruise 16-21 June 97.  Our group has the necessary
messengers, Niskin bottle adaptors, and wire adaptors to fit either winch
setup aboard the Sproul.

	The CTD operation involves continuous 12 hour sampling at each of
six stations.   We require a winch that will be able to operate in this
mode.  We used the .322 wire CTD winch last summer without any problems. 

	We may need to dive on some of the moorings.  I will turn in a
dive request notification to Ship's Scheduling.  Most of the diving for
this project is performed from small boats launched from the SIO pier.

***	This is a preliminary cruise plan.  A more complete version will be
sent in a couple of days as the details are worked out.	***


Objectives:

1.  Deploy subsurface moorings at the T500, T350, T120, T70
locations along an East-West transect from the Mission Bay jetty where the
number denotes the deployment depth.  These acoustically released moorings
contain ADCPs and temperature loggers.

2.  Perform 12 hour continuous CTD samplings at the T500, T350, T120,
T70, T30, and TBN stations. 

3.  Deploy a subsurface mooring at the T15P site (Pineda thermistor
chain site near the T15 site.

4.  Recover the T17, T23, T27 subsurface moorings.

5.  Collect continuous underway met data.

Schedule

16 June 
	0900	Lv Marfac
	1100	Begin mooring operations 
		(4 deployments @ 2 hours each)
	2000	Begin T500 CTD cast

17 June
	0900	begin T350 cast
	2200	begin T120 cast

18 June
	1100	begin T70 cast

19 June 
	0000	begin T30 cast
	1300	recover T17, T23, T27 moorings
		deploy T15A mooring
	1700	begin TBN CTD cast

20 June 
	0600	complete TBN CTD cast
		weather day allowance

21 June
	0900	arrive at Marfac

Personnel

	Paul Harvey		Chief Scientist,		CCS
				Development Engineer		
	Charles Coughran	Development Engineer		CCS
	Chris Freimuth		Development Technician		CCS
	Daniel Jackson		Marine Technician		CCS
	Erika Lawson		Programmer/Analyst		CCS
	Jim Lerczack		Graduate Student		CCS
	John Lyons		Development Technician		CCS
	Grant Mills		Development Engineer		CCS
	TBN			Graduate Student		CCS
	Shannon Scott		Development Technician		CCS
	TBN			Resident Technician		STS

Shiploading Friday, 13 June 97

	Item				Weight(lbs)	Total Weight

1.	6 each	concrete anchors	 3,000		18,000

2.	6 each subsurface floats	   500		 3,000

3.	1 each 20' seavan		12,000		12,000

4.	1 basket rigging		 1,000		 1,000

5.	3 crates instruments, computers	   500		 1,500


					Total 35,500 lbs

Cruise Prep on Loading Day
	
	Load scientific gear
	Hang mooring block, ctd block, and stopper chain from A-frame
	Rig, wire, and test CTD system and winch
	Rig trawl winch with trash drum and working wire
	Set up dual underway met stations on O-2 deck
	Install and check out CTD, Met, and ADCP computers
	Set deck and trawl winch for first deployment
	Tie down gear for sea

Please address questions and comments to:
	
	Paul J. Harvey
	x44540
	pjh@coast.ucsd.edu or pharvey@ucsd.edu
	



Email: shipsked@ucsd.edu