Date: Thu, 18 Jun 1998 09:15:49 -0700 X-Sender: et@purple Mime-Version: 1.0 To: shipsked@ucsd.edu From: Eric TerrillSubject: cruise plan for Terrill cruise on Sproul, 7/10-19 The following is a tentative cruise plan for our upcoming cruise. I've tried to contact the res-techs to discuss our plans,needs, etc. but haven't been able to reach them yet. I will be out of town the week of 6/22-26. Thanks, -Eric tentative cruise plan: R/V Sproul, dates: July 10-19. Chief Scientist: Eric Terrill, x41085 July 8: begin loading vessel in afternoon July 9: load vessel, mount Niiler's meteorological mast to bow (requires MARFAC crane) July 10: depart San Diego MARFAC pier early morning (etd 7am), steam to Coho anchorage July 11: arrive Coho anchorage (eta. 8am), deploy DGPS station at Government Point, testing of buoy system, practice deployments, towing, and recoveries, check data integrity, spend evening in Coho Anchorage July 12: deploy buoy systems in a.m., obtain data, check telemetry systems, recover buoys late afternoon spend evening in Coho Anchorage July 13: deploy buoy systems in a.m., deploy Niiler drifter, coordinate over-flights with MASS aerial system out of Lompoc (will be weather dependent, but most likely to occur in afternoon when winds are strongest, recover buoys late afternoon, spend evening in Coho Anchorage July 14: deploy buoy systems in a.m., deploy Niiler drifter, coordinate over-flights with MASS aerial system out of Lompoc (will be weather dependent, but most likely to occur in afternoon when winds are strongest), recover buoys late afternoon, spend evening in Coho Anchorage July 15: deploy buoy system in a.m., deploy Niiler drifter, coordinate over-flights with MASS aerial system out of Lompoc (will be weather dependent, but most likely to occur in afternoon when winds are strongest), recover buoys late afternoon, spend evening in Coho Anchorage July 16: deploy buoy system in a.m., deploy Niiler drifter, recover buoys late afternoon, spend evening in Coho Anchorage July 17: deploy buoy system in a.m., deploy Niiler drifter, recover buoys late afternoon, spend evening in Coho Anchorage July 18: deploy buoy system in a.m., deploy Niiler drifter, recover buoys late afternoon, recover DGPS system from Government Point, begin transit to San Diego July 19: arrive San Diego in evening July 20: offload RV Sproul equipment required from ship/res - techs á 7/16" wire on trawl winch á trawl block in A-frame á air-tuggers (2) á capstan á 12' zodiac (or similar) for landing on Coho beach to setup DGPS system on Government point