Cruise Plan

WINANT CRUISE PLAN

Date: Wed, 17 Jun 1998 11:15:52 -0700 (PDT)
From: Paul Harvey 
Reply-To: Paul Harvey 
To: Louis Zimm , Marine Facilities Shop ,
        resident technicians , shipsked@ucsd.edu,
        rknox@ucsd.edu
Cc: wpawelak@ucsd.edu, mms-field@coast.ucsd.edu,
        Clinton Winant ,
        "Myrl C. Hendershott" ,
        Ed Dever , Brynn Craffey ,
        Erika Lawson ,
        "Brett N. Lesh" ,
        John Lyons , Jerome Wanetick ,
        Dan Larsen , Charles Coughran ,
        Jennifer Davis 
Subject: Cruise Plan - MMS #17 (fwd)
Mime-Version: 1.0


*******************

Please Note:

1.	This cruise will have two legs:

	Leg 1 24 June - 30 June, SD - Port Avila, Avila Beach	
		12 scientists + 1 res tech

	Leg 2 30 June - 3 July, Port Avila, Avila Beach to SD
		10 scientists + 1 res tech

2.	Chief Scientist Leg 1 - Clinton Winant

	Chief Scientist Leg 2 - Ed Dever

3.	No port facilities are required at Avila Beach.  CCS personnel
	have arranged and paid for the water taxi service at Avila Beach
	to facilitate transfer of personnel.

4.	Gear will arrive on two 40' flatbed loads @ MarFac on tuesday 23
	June.

5.	Contacts

		Scientific:
			Clinton Winant	cwinant@ ucsd.edu	x42067
			Ed Dever	dever@coast.ucsd.edu	x48091

		Operations:
	
			Paul Harvey	pharvey@ucsd.edu	x44540

********************


---------- Forwarded message ----------
Date: Tue, 26 May 1998 15:58:36 -0700 (PDT)
From: Clinton Winant 
To: pjh@coast.ucsd.edu, dever@coast.ucsd.edu, erika@coast.ucsd.edu,
    mch@coast.ucsd.edu
Cc: brynn@coast.ucsd.edu
Subject: Cruise Plan

Oooops!


MMS Cruise 17   R/V Sproul     24 June - 3 July 1998


Cruise Goals

This is a mooring ops and survey cruise focused on the area between
Port Hueneme and Port San Luis, CA. The plan calls for evening
departure on 24 June. If this is not possible, plan will be
revised. Diving ops may be required in the event of mooring failure.

	Leg 1 SD - Avila Beach		Leg 2 Avila Beach - SD


mooring acronyms:
AB = Avila Beach
AN = Anacapa Island
AR = Pt. Arguello
CA = Carpinteria
GO = Goleta Pt.
IN = inshore
MB = Morro Bay
MI = middle
OF = offshore
RO = Santa Rosa Island
SA = Pt Sal
SM = San Miguel Island

24 June     2000 leave Nimitz Marfac, transit to ANMI

25 June     1200 Deploy and Recover ANMI
	    1600 Depart for SMOF

26 June     0600 Deploy and Recover SMOF
	    0900 Begin SMOF-SMIN CTD line
	    1700 Deploy and Recover SMIN
	    2400 Depart for AROF

27 June     0600 Deploy and Recover AROF
	    1000 Depart for ARMI
	    1300 Deploy and Recover ARMI
	    1700 Depart for ARIN
	    1900 Deploy and Recover ARIN

28 June     0600 Deploy and Recover SAOF
	    1000 Depart for SAMI
	    1300 Deploy and Recover SAMI
	    1700 Depart for SAIN
	    1900 Deploy and Recover SAIN

29 June     0600 Deploy and Recover ABOF
	    1000 Depart for ABMI
	    1300 Deploy and Recover ABMI
	    1700 Depart for ABIN
	    1900 Deploy and Recover ABIN

30 June	    0600 Catch up any unfinished mooring work
	    1200 Exchange personnel in Avila Beach
	    1800 Leave for SAIN
	    2100 Begin SAIN-SAOF CTD line
	    
 1 July	    0500 End CTD line steam to ABOF
	    0800 Begin ADCP/XBT survey

 2 July	    2300 End ADCP/XBT survey at ANOF
	    2330 Begin ANIN-ANOF CTD line

 3 July	    0300 End CTD line.  Depart for MARFAC
	    1800 Tie-up MARFAC


Personnel           

	Leg 1				Leg 2

1	Winant	    			**
2	Hendershott			**
3	Dever				Dever
4	Harvey				Harvey	
5	Alden				Alden
6	Crosby				Crosby
7	keif				keif
8	Jackson				Jackson
9	Lyons				Lawson
10	Aim				Aim
11	skip				Lesh
12	jss				jss

	restech				restech

********


Sproul Loading List during 23-24 June for MMS Cruise #17
during 25 June - 3 July 1998.  The Sproul is due in on monday morning and
should be available for loading of computers, underway mets, and survey
gear on tuesday 23 June.  The crane loading will take place on tuesday
and wednesday, 23-24 June as required.  We will send the mooring and other
gear requiring crane loading to MarFac on tuesday in two loads of a 40'
flat bed truck.  Offloading in San Diego will take less than one day.  

	ITEM		Size (h x w x l, feet)	Wt (lbs)	Total Weight


5	surface buoys		6x5x5		1600		 8,000		

4	anchors			3x4x4		2800		11,200

5	buoy towers		9x2x2		200		 1,000

3	chain baskets		3x4x4		2800		 8,400

1	rigging basket		3x4x4		2000		 2,000

1	drifter basket		4x4x5		 900		   900

1	wire rope pallet	3x4x8		2200		 2,200

2	wire rope spoolers	4x4x5		 800		 1,600

1	instrument seavan	7x7x8		5500  		 5,500

1	seavan			8x8x20	       12000		12,000


		Total Weight				52,800 lbs.

Loading and Prep on tuesday, 23 June
	
	Install and test underway/over-the-side restech ADCP
	Install and test underway met systems
	Set up data acquisition computers and systems in dry and wet labs
		(met, CTD, XBT, ADCP, general computers, micromariner, 	
		printers, cell tel)

Loading and Prep with help from ResTech Group and MarFac Personnel on
tuesday/wednesday 23-24 June

	Load scientific gear on deck
	Hang trawl block in A-frame center, stopper chain in A-frame port side
		(1/2" x 23' chain, CCS to provide)
	Load trash drum onto trawl winch w/ 200-500' of 9/16" 3x19  terminated
		working wire
	Set up deck capstan
	Provide CTD winch and set up with wire/slip rings for Neil Brown CTDs


CCS Personnel

	Install towers, Argos, and lanterns on buoys
	Install top VMCMs to Buoy Argos for satellite data test
	Check out VMCMs, PSensors, TLoggers, kcells
	Tie down deck gear and gear in lab spaces

Internet: shipsked@ucsd.edu