Toms,
I have a tentative schedule and service arrangement with SIO MPL to use
the R/V New Horizon for the upcoming SAN2 sea test in December. The deployment
dates are 6-7 December and the recovery dates are 20-21 December, with
mobilization and demobilization dates on both sides of these periods.
Capt. Althouse, the Marine Superintendent, is willing to accommodate our
special needs by allowing us to start after midnight on the first day
in order to accomplish the fathometer survey before we enter normal daytime
operations on 6 December. A similar schedule would be desirable on 20
December so that we could perform surface target runs with the ship prior
to recovery. Because of the University National Observatory Laboratory
Ship (UNOLS) rules under which this and the larger ships operate, and
to minimize ship's crew fatigue, it is highly desirable, and perhaps necessary,
for our scientific party to embark on the evening of the day before we
sail, and to remain on board until the cruise is completed. This is somewhat
different than we would have done with the R/V Sproul, had it been available
for this schedule. The Horizon has sufficient berthing for this, whereas
the Sproul does not.
Elizabeth Brenner and Rose Dufour, the ship schedulers, contacted John
Freitag at ONR to see if we could use his funding arrangement to support
us; however, he can accept only 6.1 funds, so we will need to make other
arrangements. We should ask ONR for advice and direction on how to proceed
here. Do we need to get competitive bids? Who should do the contracting?
Should SSC-SD proceed on its own, or should LWAD become involved now and
include the PBD in the negotiations? I'm sure Jim Curtis could do this
much better than I, but then we need to know what Dana and Dave want us
to do.
Regarding the node laydown for SAN2: We plan to deploy four nodes in a
straight line with the most shallow node in 75 meters. The remaining nodes
will be deployed to the west with even spacing, and the deepest node in
100 meters. The total distance is 2 nmi, giving a spacing of about 1235
meters between the nodes. An alternative laydown would have a shorter
spacing, but no nodes beyond 82 meters depth.
We have a workable solution to securing recovery loops to the array strength
member, as suggested by Bob Wilson. We would need to have the arrays here
a week in advance of deployment in order to install the loops. An option
is to have USSI install the loops, which may require 15 minutes each plus
some stitching. We have ordered the necessary material, and will begin
installing loops on the practice array in 2-3 weeks when the order comes
in.
I recommend that the R/V New Horizon or other ship be scheduled as soon
as possible for the PBD, since our schedule flexibility will be virtually
nil. A "final" request to SIO MPL still does not commit the
Navy to anything, but would reserve the time slot. Because we can operate
from shore in San Diego, we do not need such a large ship as we were planning
in our original location. Also, we should not need the ship continuously
between deployment and recovery. I will be happy to work with LWAD to
come up with a revised plan for ship usage.
Regards,
Ken
---------------------------------------------------------------------------------------------------------------------
SCHEDULE
The summary schedule of activities can be found below. Adjustments may
be necessary to accommodate weather and other contingencies.
MON 28 Nov All nodes received from USSI; commence node
checkout & crypto load
TUE 20 Nov
WED 30 Nov
THU 1 Dec All deployment/recovery equipment ready
FRI 2 Dec Load ship, stage equipment; dockside practice;
pre-sail conference
SAT 3 Dec All personnel board ship; conduct fathometer
survey beginning at midnight
SUN 4 Dec Practice normal deployment/recovery procedures;
deploy racom buoy, repeaters, and up to 4 ADM nodes; check out communications
MON 5 Dec Complete deployment; conduct telesonar &
release surveys at night; turn on one node; turn off three nodes; return
to port; commence data collection and surface surveillance; one node operation
with targets of opportunity, with short-term settling time
TUE 6 Dec Unload ship
WED 7 Dec Deployment backup day
THU 8 Dec Deployment backup day
FRI 9 Dec Node stabilization
SAT 10 Dec Node stabilization
SUN 11 Dec Node stabilization
MON 12 Dec Turn on three nodes; turn off one node
TUE 13 Dec Node operation with targets of opportunity,
with long-term settling time
WED 14 Dec Node operation with targets of opportunity
THU 15 Dec Node operation with targets of opportunity
FRI 16 Dec Node operation with targets of opportunity
SAT 17 Dec Node operation with targets of opportunity
SUN 18 Dec Node operation with targets of opportunity
MON 19 Dec Load ship for recovery; all recovery personnel
board ship; commence target runs after midnight
TUE 20 Dec Recover all equipment
WED 21 Dec Backup recovery day
THU 22 Dec Demobilize
FRI 23 Dec Backup day: Last day to recover and demobilize
---------------------------------------------------------------------------------------------------------------------
TEST OBJECTIVES
Objectives for this test are to ensure that the ADM hardware and software
are functioning in a manner to support the DADS PBD. Specifically, this
includes
• Verify all sensor node functions.
• Verify the quality of recorded data, including use of encryption
algorithms.
• Verify that magnetometer movement does not contribute excessive
noise to the magnetic data.
• Refine new deployment hardware and procedures.
• Measure the settling time required to stabilize magnetometers
on the sea floor.
• Test automated array element localization software.
• Test acoustic surface ship classification software.
• Demonstrate automated contact reporting.
|